Culham Hydro for Evans Energy Ltd
10 Jan 2025Pascon successfully designed, built and commissioned the connection for a 500kV Archimedean hydro generation site for Evans Energy Ltd at Culham. The project involved laying a 120-metre cable route, constructing a bespoke 11kV metered substation and connecting the site to the existing network. Pascon carried out all excavations, reinstatement and HV cable installation within schedule and budget, while acting as the key liaison between multiple stakeholders. From project award to completion in under three months, the site was fully operational before the client’s energy tariff deadline, delivering a timely and efficient solution.

Complete in under 3 months

Strategic Consultation
Background
- Design, build and commission the connection for a 500kV Archimedian hydro generation site
- Install a 120-metre cable route, construct an 11kv electric substation, and connect it to the existing network.
Solution
- We performed all excavations and reinstatement
- Designed and installed a bespoke 11kV metered substation
- Laid the HV cable—within schedule and budget
Benefit
- We served as liaison with multiple stakeholders, ensuring all processes were completed on time
- Project award to completion was less than three months
- Completed before the client energy tariff expired
+44 (0)1922 454444
