Primary Substation, Summer Lane, Birmingham
28 Sep 2025When the existing primary substation beneath an office block in Birmingham needed to be relocated following the sale of the building, a new facility was constructed 250 metres away on Summer Lane. Pascon was appointed to support this major transition, delivering trenching works and installing 300mm Triplex cables between the old and new sites. In […]
Brindley 12MW Battery Energy Storage System
10 Sep 2025The Brindley 12MW Battery Energy Storage System (BESS) required the design, installation and commissioning of a full Balance of Plant solution, metered at 33kV and connected to a primary substation over 1km away. Pascon delivered a containerised substation solution, including dual substations, switchgear and 110V battery chargers, alongside the excavation and installation of 1,250 metres […]